Scottso Corporation applies overhead using an actual costing approach. Budgeted factory overhead was $266,400, budgeted machine-hours were 18,500. Actual factory overhead was $287,920, actual machine-hours were 19,050. How much overhead would be applied to production? a. $266,400. b. $274,320. c. $279,607. d. $287,920.

+1
Answers (1)
  1. 27 April, 22:59
    0
    Option (b) is correct.

    Explanation:

    Given that,

    Budgeted factory overhead = $266,400,

    Budgeted machine-hours = 18,500

    Actual factory overhead = $287,920,

    Actual machine-hours = 19,050

    Budgeted rate:

    = Budgeted factory overhead : Budgeted machine-hours

    = $266,400 : 18,500

    = $14.4

    Overhead allocated:

    = Actual machine-hours * Budgeted rate

    = 19,050 * $14.4

    = $274,320

    Here, the allocated overhead is less than the actual factory overhead. Hence, the overhead is under-allocated.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Scottso Corporation applies overhead using an actual costing approach. Budgeted factory overhead was $266,400, budgeted machine-hours were ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.