FastNet Systems is a start-up company that makes connectors for high-speed Internet connections. The company has budgeted variable costs of $ 110 for each connector and fixed costs of $ 4 comma 500 per month. FastNet 's static budget predicted production and sales of 100 connectors in August, but the company actually produced and sold only 74 connectors at a total cost of $ 25 comma 000. FastNet 's flexible budget variance for total costs is

+4
Answers (1)
  1. 10 August, 06:15
    0
    Cost variance = $12,360 unfavorable

    Explanation:

    Giving the following information:

    Standard costs:

    Budgeted variable costs of $ 110 for each connector

    Fixed costs of $4,500 per month.

    Actual production = 74 connectors

    Total cost = $25,000

    First, we need to calculate the standard total cost:

    Standard total cost = 4,500 + 110*74 = $12,640

    Now, we can determine the flexible budget cost variance:

    Cost variance = 12,640 - 25,000 = $12,360 unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “FastNet Systems is a start-up company that makes connectors for high-speed Internet connections. The company has budgeted variable costs of ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.