Ask Question
27 September, 13:08

For the project activities below: Answer questions 44-46: Normal Crash Crashing Costs/Wk Activity Precedes Time (wk.) Times ($ 000) / Wk A C, D 6 5 8 B G 4 2 6 C E 4 4 - - D F 5 3 6 E H 6 4 8 F H 6 4 10 G I 8 6 5 H End 5 3 12 I End 6 5 5 44. What activities make up the critical path

+3
Answers (1)
  1. 27 September, 16:26
    0
    Options C and E are correct

    Explanation:

    BGI and ADFH makes up the critical path
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “For the project activities below: Answer questions 44-46: Normal Crash Crashing Costs/Wk Activity Precedes Time (wk.) Times ($ 000) / Wk A ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers