Teller Co. is planning to sell 900 boxes of ceramic tile, with production estimated at 870 boxes during May. Each box of tile requires 44 pounds of clay mix and 1/4 hour of direct labor. Clay mix costs $0.40 per pound and employees of the company are paid $12.00 per hour. What is the total amount to be budgeted for direct labor for the month? $2,610 $10,440 $2,700 $41,760

+4
Answers (1)
  1. Yesterday, 00:29
    0
    The correct answer is $2,610.

    Explanation:

    According to the scenario, computation of the given data are as follow:-

    We can calculate the the direct labor cost by using following formula:-

    Direct labor hour required = Estimated production * Direct labor hour

    = 870 * 1:4 = 217.5 hours

    Direct labor cost = Direct required labor hour * Rate of labor per hour

    = 217.5 hours * $12

    = $2,610

    According to the analysis, $2,610 is the total amount to be budgeted for direct labor.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Teller Co. is planning to sell 900 boxes of ceramic tile, with production estimated at 870 boxes during May. Each box of tile requires 44 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.