Ask Question
8 August, 22:17

A production center is available for 8 hours per day in a factory. It is comprised of several rotary parts, and the worker operating it is required to lubricate these rotary parts once each day. It takes 2 hours to remove these parts from the equipment, lubricate them, and re-assemble them. The production center is not available for production during these times. The availability of the production center is:

+4
Answers (1)
  1. 8 August, 22:59
    0
    75%

    Explanation:

    Since the production center is available for 8 hours per day in a factory, and the worker operating it is required to lubricate these rotary parts once each day.

    If it takes 2 hours to remove these parts from the equipment, lubricate them, and re-assemble them and the production center is not available for production during these times;

    Then the availability of the production center is 75% which is derived by : [8 hours total - 2 hours downtime / 8 hours total availability] x 100 = 75%
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A production center is available for 8 hours per day in a factory. It is comprised of several rotary parts, and the worker operating it is ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers