Jase Manufacturing Co.'s static budget at 7,600 units of production includes $30,400 for direct labor and $3,040 for electric power. Total fixed costs are $39,200. At 10,500 units of production, a flexible budget would show a. variable costs of $46,200 and $39,200 of fixed costs b. variable costs of $46,200 and $54,158 of fixed costs c. variable and fixed costs totaling $72,640 d. variable costs of $33,440 and $39,200

+2
Answers (1)
  1. 22 June, 09:15
    0
    a. variable costs of $46,200 and $39,200 of fixed costs

    Explanation:

    Given that

    Direct labor cost = $30,400

    Electric power = $3,040

    Fixed cost = $39,200

    So, The computation of the variable cost and the fixed cost is shown below:

    The variable cost is

    = (Direct labor + electric power) : production units * estimated production units

    = ($30,400 + $3,040) : 7,600 units * 10,500 units

    = $46,200

    And, the fixed cost is $39,200
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Jase Manufacturing Co.'s static budget at 7,600 units of production includes $30,400 for direct labor and $3,040 for electric power. Total ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.