Accurate Tax Returns budgets two direct labor hours for every tax return that it prepares, at a standard cost of $ 32 an hour. During the most recent year, 540 returns were completed with the labor cost totaling $ 26 comma 000. The actual labor cost was $ 48.15 per hour during that period. The actual number of labor hours was 1 comma 000. What is the direct labor cost variance?

+2
Answers (1)
  1. 12 June, 20:06
    0
    Labor cost variance refers to the variance, which is determined by subtracting the actual direct labor cost from the standard direct labor cost associated with the product.

    Explanation:

    Given that:

    Actual hours = 1,000

    Actual rate = $48.15

    Standard rate = $32 per hr.

    Now,

    Labor Cost variance = Actual hours * (Actual rate - Standard Rate)

    Labor Cost variance = 1000 * (48.15 - 32)

    Labor Cost variance = 1000 * 16.15

    Labor Cost variance = 16,150
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Accurate Tax Returns budgets two direct labor hours for every tax return that it prepares, at a standard cost of $ 32 an hour. During the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.