Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October are available: 5,000 hrs. Quantity of direct labor used Actual rate for direct labor $22.75 per hr. 800 bicycles Bicycles completed in October Standard direct labor per bicycle 6.0 hrs. Standard rate for direct labor $24.00 per hr. a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Favorable - 6,250 Direct Labor Rate Variance Unfavorable $ 4,800 Direct Labor Time Variance Favorable $ х Total Direct Labor Cost Variance b. How much direct labor should be debited to Work in Process?

+1
Answers (2)
  1. 28 February, 23:49
    0
    Direct Labor Rate variance = - 6250 fav

    Direct labor time variance = 4800 Unfavorable

    Total Direct Labor Cost Variance-1450 fav

    Work In Process 116650 Dr.

    Explanation:

    Glacier Bicycle Company

    Direct Labor Rate variance = (actual hours * actual rate) - (actual hours * standard rate)

    Direct Labor Rate variance = (5000 * 22.75) - (5000*24)

    Direct Labor Rate variance = $113750 - 120,000 = - 6250 fav

    Direct Labor Rate variance = - 6250 fav

    Direct labor time variance = (actual hours * standard rate) - (standard hours * standard rate)

    Direct labor time variance = (5000 * 24) - (4800 * 24)

    Direct labor time variance = 120,000-115200

    Direct labor time variance = 4800 Unfavorable

    Total Direct Labor Cost Variance = Direct Labor Rate variance + Direct labor time variance = - 6250 fav + 4800 Unfavorable = - 1450 fav

    b. The journal entry would be

    Work In Process 116650 Dr.

    Direct Labor Cost Variance 1450 Cr

    Payroll 115200

    Direct Labor Debited to Work In Process = $116650
  2. 29 February, 01:52
    0
    a) Direct labor rate variance

    =5000 * (22.75-24)

    =-$6250 Favorable

    Direct labor time variance

    =24 * (5000-800*6)

    =$4800 Unfavorable

    Total Direct labor cost variance

    = (5000*22.75) - (800*6*24)

    =-$1450 Favorable

    b) Direct labor debited to Work in process

    =800*6*24

    =115200
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Direct Labor Variances Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October are ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.