In December 2014, Shire Computer's management establishes the 2015 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $747,500 of overhead costs and $575,000 of direct labor cost in year 2015. During March 2015, Shire began and completed Job No. 13-56. 1. What is the predetermined overhead rate for year 2015?

+5
Answers (1)
  1. 20 September, 12:13
    0
    Estimated manufacturing overhead rate = $1.3 per direct labor dollar.

    Explanation:

    Giving the following information:

    Estimated overhead cost = $747,500

    Estimated direct labor cost = $575,000

    To calculate the estimated manufacturing overhead rate we need to use the following formula:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 747,500/575,000 = $1.3 per direct labor dollar.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In December 2014, Shire Computer's management establishes the 2015 predetermined overhead rate based on direct labor cost. The information ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.