Sleep master, inc. manufactures bedding sets. the budgeted production is for 57,000 comforters in 2013. each comforter requires 6 yards of material. the estimated january 1, 2013, beginning inventory is 31,000 yards. the desired ending balance is 27,000 yards of material. if the material costs $1.50 per yard, determine the materials budget for 2013.

+1
Answers (1)
  1. 21 October, 09:11
    0
    Total Material cost = $507,000

    Explanation:

    Material budget shows the total budgeted material cost for a specific period.

    Sleep master, inc.

    Direct Material Budget

    December 31, 2013

    Budgeted production units 57,000

    yards required per comforter * 6

    Materials needed for production = 342,000 yards

    Add: Ending Material Inventory = 27,000 yards

    Total Material units required = 369,000 yards

    Less: Beginning Materials = (31,000) yards

    Material used = 338,000 yards

    Cost per yard * $1.50

    Total Material cost = $507,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Sleep master, inc. manufactures bedding sets. the budgeted production is for 57,000 comforters in 2013. each comforter requires 6 yards of ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.