For July, White Corporation has budgeted production of 10,950 units. Each unit requires 0.20 direct labor-hours at a cost of $6.20 per direct labor-hour. How much will White Corporation budget for labor in July?

+4
Answers (1)
  1. 12 February, 20:00
    0
    Answer: $13,578

    Explanation:

    Each unit requires 0.2 direct labour hours to complete. There are 10,950 units to be produced.

    Calculating the amount of labor hours needed would therefore be,

    = 10,950 * 0.2

    = 2,190 labor hours would be needed.

    If labor costs $6.20 per direct labor hour and 2,190 hours are needed, calculating would be,

    = 2,190 * 6.2

    = $13,578

    $13,578 should be budgeted for labor in July.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “For July, White Corporation has budgeted production of 10,950 units. Each unit requires 0.20 direct labor-hours at a cost of $6.20 per ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.