Ask Question
Today, 08:55

Bachmann Products, Inc., has found that new products follow a learning curve. The first two units have been completed with the following results: Units Produced Marginal Labor Time 1 80.00 2 68.00 How much time will be needed to complete the 4th unit?

a. 74.00 hours.

b. 57.80 hours.

c. 56.00 hours.

d. 54.40 hours

+3
Answers (1)
  1. Today, 12:06
    0
    Time needed to complete the 4th unit = 57.80 hours

    Explanation:

    The learning curve theory states that as the cumulative output doubles the cumulative average time taken till date is reduced to a certain percentage of the previous time. This percentage is called learning rate

    Total time = Average time * cumulative number of units

    The cumulative average time is determined using the formula below:

    Y = aX^b

    a - time taken for the first unit produced

    b = log LR/Log 2

    X - cumulative units till date

    Y - cumulative average time taken for X units

    LR - Learning rate

    LR = 68/80 = 0.85 = 85%

    Time needed to complete the 4th unit

    = Learning rate * time take for the 2 unit

    = 85% * 68

    = 57.80 hours

    Time needed to complete the 4th unit = 57.80 hours
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Bachmann Products, Inc., has found that new products follow a learning curve. The first two units have been completed with the following ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers