The production budget for Manner Company shows units to be produced as follows: July, 530; August, 590; and September, 450. Each unit produced requires two hours of direct labor. The direct labor rate is currently $17 per hour but is predicted to be $17.75 per hour in September. Prepare a direct labor budget for the months July, August, and September.

+5
Answers (1)
  1. 15 November, 18:11
    0
    Direct labor budget for the months July, August, and September are $18,020, $20,060 and $15,975 respectively.

    Explanation:

    July direct labor budget = 530 * 2 * $17 = $18,020

    August direct labor budget = 590 * 2 * $17 = $20,060

    September direct labor budget = 450 * 2 * $17.75 = $15,975

    Therefore, direct labor budget for the months July, August, and September are $18,020, $20,060 and $15,975 respectively.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The production budget for Manner Company shows units to be produced as follows: July, 530; August, 590; and September, 450. Each unit ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers