Abbe Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 2,100 units and of Product B is 1,200 units. There are three activity cost pools, with estimated costs and expected activity as follows: Activity Cost Pools Estimated Overhead Cost Expected Activity Product A Product B Total Activity 1 $ 60,791 1,600 1,500 3,100 Activity 2 $ 83,421 2,600 1,300 3,900 Activity 3 $ 97,442 840 820 1,660 The overhead cost per unit of Product B is closest to: (Round your intermediate calculations to 2 decimal places.)

+3
Answers (1)
  1. 9 May, 21:41
    0
    The overhead cost per unit of product B is $84.20

    Explanation:

    Abbé company

    Product A & B

    Activity 1 to 3 respectively:

    Estimated Overhead cost $60,791

    Estimated Overhead cost $83,421

    Estimated Overhead cost $97,442

    Total Estimated overhead cost = $241,654

    Expected Activity 3,100

    Expected Activity 3,900

    Expected Activity 1,660

    Total expected Activity = 8,660

    Overhead Costs Per Activity = $241,654 / 8,660 = $27.91

    Product B

    Total Activity = 1,500 + 1,300 + 820 = 3,620

    Therefore total overhead cost = $27.91 x 3,620 = $101,034.20

    Product B sales and Production units in the period equals 1,200 units ... this means our overhead cost per unit =

    $101,034.2 divided by 1,200 units

    = $84.20
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Abbe Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 2,100 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.