The critical path on a project can change as the project progresses. select one:

a. true

b. false

+1
Answers (1)
  1. 22 February, 11:46
    0
    The answer is True.

    In project management, critical path refers to a sequence of stages that would require the smallest amount of time possible to bring a project to completion.

    Critical path can change during a project since there might be circumstances during it which would lead certain activities to be finished longer or faster. Critical path can be determined by a specialized algorithm technique.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The critical path on a project can change as the project progresses. select one: a. true b. false ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.