Which of the following is considered an organizational blueprint, which prescribes the quantity and time frame for when each end product will be assembled? WBS (Work Breakdown Structure) MRP (Material Requirements Plan) MPS (Master Production Schedule) ERP (Enterprise Resource Planning)

+3
Answers (1)
  1. 11 February, 13:15
    0
    The correct answer for the question that is being presented above is this one: "MPS (Master Production Schedule)." MPS is considered an organizational blueprint, which prescribes the quantity and time frame for when each end product will be assembled.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which of the following is considered an organizational blueprint, which prescribes the quantity and time frame for when each end product ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.