What are the consequences to the schedule if completion of a primary task is delayed?

A. The beginnings of all related dependent tasks are also delayed.

B. Time to complete the dependent task will have to be shortened.

C. The entire project schedule will be delayed.

D. The Chief Finance Officer of the divisional office.

+1
Answers (1)
  1. 14 July, 23:27
    0
    A I think dont trust me though but i think a
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “What are the consequences to the schedule if completion of a primary task is delayed? A. The beginnings of all related dependent tasks are ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.