Cinram machines has the following estimates for its new gear assembly project: price = $1,340 per unit; variable costs = $348 per unit; fixed costs = $5.1 million; quantity = 82,000 units. suppose the company believes all of its estimates are accurate only to within ± 5 percent. what value should the company use for its total variable costs when performing its best-case scenario analysis

+2
Answers (1)
  1. 24 September, 11:42
    0
    Given:

    Price per unit : 1,340

    variable cost per unit: 348

    fixed cost: 5.1 million

    quantity produced: 82,000 units

    estimate: + 5 percent

    Total variable cost: (82,000) (1.05) (348) (0.95) = 28,464,660

    Considering the accuracy of the estimate, the total variable cost is $28,464,660.00
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Cinram machines has the following estimates for its new gear assembly project: price = $1,340 per unit; variable costs = $348 per unit; ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers