There are two activities on your schedule, which are: 1) install server in lab 2) move server into the data center. however, the second task can't start until the server has run in the lab for 5 days without failure. this is an example of what?

+5
Answers (1)
  1. 22 September, 18:07
    0
    Quality Assurance or testing.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “There are two activities on your schedule, which are: 1) install server in lab 2) move server into the data center. however, the second ...” in 📘 Computers and Technology if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.