Read the following scenario: A project will require more people than originally estimated. Identify the possible risks to the project.

a.) Ideas and Creativity

b.) Money and resources

c.) Policies and Procedures

d.) Time and work ethic

+5
Answers (1)
  1. 8 November, 22:12
    0
    The correct answer is b. Money and Resources because the more people involved in a project then the more money being invested.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Read the following scenario: A project will require more people than originally estimated. Identify the possible risks to the project. a.) ...” in 📘 Computers and Technology if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.