Sayeed needs to ensure that his manager is up to date on his progress and wants to send a Status Report for a particular task. In which command group will he find this option within the Task form?

+2
Answers (1)
  1. 25 July, 16:47
    0
    Project - -> status - -> status date

    Explanation:

    If we want to share the status of a task or an entire project in Microsoft project, we can use the status date, and we could get theoretical progress, in addition, we could add progress about two dates.

    For example:

    If we have a construction, this construction will take 100 days, we could show the progress in the first two months, 60 days, in this case, would be 60% of progress, this would be in date format, 21/01/2020 to 21/03/2020.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Sayeed needs to ensure that his manager is up to date on his progress and wants to send a Status Report for a particular task. In which ...” in 📘 Computers and Technology if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers