Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year. This may lead to a project that must be done faster than anticipated. This is an example of reducing project duration caused by?

+2
Answers (1)
  1. 19 March, 09:23
    0
    Imposed project deadlines.

    Explanation:

    The term of project management imposed deadline refers mainly to the calendar-based dividing line used to determine a fixed time or date on which the project management team has projected and/or developed that the particular schedule of work and/or schedule of work events.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be ...” in 📘 Computers and Technology if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers