Which of the following is a disadvantage of the waterfall model of SDLC?

How it handles requirement changes

The required amount of rigorous attention to detail and process

The role it gives to key stakeholders

Its age

+4
Answers (2)
  1. 19 June, 01:12
    0
    Phases of waterfall model are Requirement analysis system design implementation testing, deployment maintenance.

    Explanation:

    Waterfall model should be chosen when the requirement is fixed. It is not suitable for rapid development as well for the requirement which keep on changes.

    Even the technology should not be dynamic. This also expects the project should be short. Another disadvantage is that it is difficult to measure the progress within stages.

    It is not suitable for object-oriented projects. Here the process is completed phase by phase and one at a time.
  2. 19 June, 02:53
    0
    How it handles requirement changes
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which of the following is a disadvantage of the waterfall model of SDLC? How it handles requirement changes The required amount of rigorous ...” in 📘 Computers and Technology if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.