A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario, which of the following is correct? There are four paths in this network. (T/F)

+1
Answers (1)
  1. 21 November, 01:39
    0
    True

    Explanation:

    There are four paths in this network. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate ...” in 📘 Computers and Technology if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.