Crashing almost always accelerates the schedule while increasing project risk, whereas fast tracking almost always accelerates the schedule while increasing project cost. A. TrueB. False

+3
Answers (1)
  1. 16 September, 02:28
    0
    Answer: False

    Explanation: Because fast-tracking doesn't involve additional resources, it's usually best to start with this technique while Crashing requires careful planning to prevent "panic mode" among the project crews and to avoid acceleration claims.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Crashing almost always accelerates the schedule while increasing project risk, whereas fast tracking almost always accelerates the schedule ...” in 📘 Computers and Technology if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.