Select the correct answer.

In which phase does the development team check the project for error handling capabilities?

A, design

B, testing and delivery

C, development

D, maintenance

+4
Answers (1)
  1. 26 March, 08:09
    0
    B

    Explanation:

    engineers design and carry out test cases and evaluate exit criteria (by following the scope set in the planning phase). They create bug reports describing detected defects and report to the stakeholders on the test findings and the completion status. Testing may be repeated to check for errors.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Select the correct answer. In which phase does the development team check the project for error handling capabilities? A, design B, testing ...” in 📘 Computers and Technology if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.