Your co-worker is envisioning a new computer with an increased clock rate that will be able to run a daily log program in 2 seconds. Currently this log program requires 5 seconds to complete on an old computer running a 4 GHz clock. Provided the new computer requires 1.6 times as many clock cycles as the old computer what will be the target clock rate for the new computer

+4
Answers (1)
  1. 19 April, 18:42
    0
    16GHz

    Explanation:

    Given that to complete daily log program (P) in Old comoputer take 5 seconds and clock frequency is 4 GHz

    since 1 second thake 4x109 colck cylce.

    so 5 second take : 5x4x109 clock cycle (Total number of clock cycle needs to complete P).

    As given in question New computer can take 1.6 x 5x4x109 clock cycle to complete in 2 second.

    So:

    in 2 second number of clock cycle can complete is : 1.6 x 5x4x109

    so in 1 second number of clock cycle can complete is : (1.6 x 5x4x109) / 2 = > 1.6 x 5x2x109 = >8x2x109 = > 16x109 = >16GHz.

    So new computerwill have 16GHz. clock rate
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Your co-worker is envisioning a new computer with an increased clock rate that will be able to run a daily log program in 2 seconds. ...” in 📘 Computers and Technology if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.