Ask Question
1 April, 15:51

With 10,000 per day who would be the apparent low bidder; Bidder A was $500,000 and estimated completion date of 200 days. Bidder B was $540,000 and a completion day and estimated completion date of 180.

1. Bidder B

2. Bidder A

+2
Answers (1)
  1. 1 April, 16:39
    0
    Bidder B is the lower bidder. the option (A) is correct

    Explanation:

    Solution

    Given that:

    Bidder A = $500,000

    The estimate completion time = 200 days

    Bidder B = $540,000

    The estimate completion time = 180 days

    Overhead charges = $10,000/day

    Now,

    The Total Bid of A (including overhead charges) = 500,000 + 200 * 10000

    = 500,000 + 2000000

    =$2,500,000

    The Total Bid for B (Including overhead charges) = 540,000 + 180 * 10000

    =540,000 + 1,800,000

    =$2340000

    Hence Bidder B is apparently a low bidder, since the Total Bid of B is lower than the Total Bid of A.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “With 10,000 per day who would be the apparent low bidder; Bidder A was $500,000 and estimated completion date of 200 days. Bidder B was ...” in 📘 Engineering if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers