With 10,000 per day who would be the apparent low bidder; Bidder A was $500,000 and estimated completion date of 200 days. Bidder B was $540,000 and a completion day and estimated completion date of 180.
1. Bidder B
2. Bidder A
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “With 10,000 per day who would be the apparent low bidder; Bidder A was $500,000 and estimated completion date of 200 days. Bidder B was ...” in 📘 Engineering if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.