The construction time for a bridge is weather dependent. The project is expected to take 150 days if the weather is dry and hot. If the weather is damp and cool, it is expected to take 350 days. Otherwise, it is expected to take 300 days. Historical data suggests that there is a 40% chance of cool damp weather and a 10% chance of hot dry weather. What is the expected completion time of the project? g

+2
Answers (1)
  1. 21 February, 03:04
    0
    The expected completion time of the project is 305 days

    Explanation:

    Given

    Expected days = 150, if the weather is dry and hot.

    Expected days = 350, If the weather is damp and cool

    Otherwise, it is expected to take 300 days.

    Chance of cool damp weather = 40%

    Chance of hot dry weather = 10%

    Chance of other weather = 100% - 40% - 10% = 50%

    The expected completion time of the project is calculated as follows;

    (Expected days when cool and damp) + (Expected days when hot and dry) + (Others)

    = 350 * 40% + 150 * 10% + 300 * 50%

    = 305 days

    The expected completion time of the project is 305 days
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The construction time for a bridge is weather dependent. The project is expected to take 150 days if the weather is dry and hot. If the ...” in 📘 Engineering if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.