A worker is hired for $80 a day on the condition that if business is slow, the worker will only receive half pay. At the end of 20 days, the worker receives $1,320. On how many days was business slow?

+2
Answers (1)
  1. 18 August, 00:17
    0
    7 slow days

    You know the worker worked a total of 20 days, some at $80 per day, and some at $40 per day. After the 20 days, the worker was paid $1320.

    x = days paid full time ($80)

    y = days paid half time ($40)

    you have two unknowns, so you'll need two equations to solve, from the problem statement, we can derive the following relationships:

    ($80) x + ($40) y = $1320

    x + y = 20 days

    x = 20 - y

    80 (20 - y) + 40y = 1320

    1600 - 80y + 40y = 1320

    1600 - 40y = 1320

    1600 - 1320 = 40y

    280 = 40y

    y = 280/40 = 7

    thus 7 days paid half time (i. e. slow days)

    verify your solution is correct

    y = 7

    x = 20 - 7 = 13

    80 (13) + 40 (7) = 1320 [OK]
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A worker is hired for $80 a day on the condition that if business is slow, the worker will only receive half pay. At the end of 20 days, ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.