If a crew of 4 workers complete the job in 10 hours, how long will it take 5 workers to complete the same job?

+1
Answers (1)
  1. 22 June, 02:24
    0
    Your answer would be 8. It would take them 8 hours to complete the same job.

    5x=4 (10) = 40

    x=8

    8 is your answer!
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If a crew of 4 workers complete the job in 10 hours, how long will it take 5 workers to complete the same job? ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.