The first painter can finish a paint job in 2 hours. The second painter can finish the same job in 8 hours. How long would it take them to finish the job if they were working together?

+3
Answers (1)
  1. 28 October, 00:29
    0
    I believe it takes 1 3/5 hrs for them to finish the job together
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The first painter can finish a paint job in 2 hours. The second painter can finish the same job in 8 hours. How long would it take them to ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.