If 6 workers can cut the grass in 4 hours, how many workers will be needed to cut the grass in 3 hours?

A. 2 workers

B. 8

C. 12

D. 24

+4
Answers (1)
  1. 26 June, 09:57
    0
    The answer for this question is B
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If 6 workers can cut the grass in 4 hours, how many workers will be needed to cut the grass in 3 hours? A. 2 workers B. 8 C. 12 D. 24 ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.