A work cell is scheduled to build 120 digital light processor (dlp) assemblies each week. these assemblies are later installed into home theater projection systems. the work cell has 7.5 hours of productive work each day, six days per week. what is takt time for this cell? express your answer in minutes rounded to one decimal place.

+1
Answers (1)
  1. 29 November, 11:40
    0
    Work cell produces 120 digital light processors in a week. We want to find the time spent on each processor in minutes. So for this first we will find the total time spent on 120 processors in a week.

    Number of productive hours in a day = 7.5

    Working days per week = 6

    So, number of productive hours per week = 6 x 7.5 = 45 hours

    1 hour = 60 minute

    So, number of productive minutes per week = 45 x 60 = 2700 minutes

    120 processors are produced in time = 2700 minutes

    1 processor is produced in time = 2700/120 minutes = 22.5 minutes

    So, it takes 22.5 minutes to produce one digital light processor
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A work cell is scheduled to build 120 digital light processor (dlp) assemblies each week. these assemblies are later installed into home ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.