N operation has a 10 percent scrap rate. as a result, 72 pieces per hour are produced. what is the potential increase in labor productivity that could be achieved by eliminating the scrap

+2
Answers (1)
  1. 12 February, 14:43
    0
    100% - 10% = 90%

    90% = 0.90

    72/0.90 = 80

    they should produce 80 parts per hour which is an 8 part increase
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “N operation has a 10 percent scrap rate. as a result, 72 pieces per hour are produced. what is the potential increase in labor productivity ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.