It takes an electrician 45 minutes to wire an office in a new office building that is being built. The electrician signed a contract to wire all offices on 6 floors of the new building. There are 50 offices on each floor. How many weeks should the electrician allow for this job if he works a standard work week (8 hours per day for 5 days a week) ? Express the answer in decimal form rounded to the tenth place.

+1
Answers (1)
  1. 6 June, 02:39
    0
    45/60*6*50=x hours

    x=225

    x/8=y days

    y/5=z weeks the electrician should allow 5.625 weeks for this job.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “It takes an electrician 45 minutes to wire an office in a new office building that is being built. The electrician signed a contract to ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.