A road crew can repave 1/48 of a road each hour. they must repave a road that is 3/8 miles long. how long will it take the crew to repave the road?

+4
Answers (1)
  1. 18 January, 07:45
    0
    3/8 / 1/48 = 3/8 x 48/1 = 144/8 = 18 hours
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A road crew can repave 1/48 of a road each hour. they must repave a road that is 3/8 miles long. how long will it take the crew to repave ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.