If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

+2
Answers (1)
  1. 17 August, 01:02
    0
    5 times 100 = 500

    500 divided by 20 = 25

    25 containers
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.