Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

+4
Answers (1)
  1. 10 June, 22:24
    0
    4 additional workers for 7 total workers.

    if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12 = 7 total workers. 7-3 = 4 additional workers needed.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours? ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.