One crew can seal a parking lot in 12 hours and another in 15 hours. how long will it take to seal the parking lot if the two crews work together?

+4
Answers (1)
  1. 11 March, 00:15
    0
    This is a typical work problem in algebra. The approach to this is using the equation: Rt = 1, where R is the rate per person working, t is the amount of time worked by an individual. All their rates must equal to 1. The solution is as follows:

    12/x + 15/x = 1

    Solving for x,

    x = 27 hours

    So, if they work together, they can finish the work in 27 hours.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “One crew can seal a parking lot in 12 hours and another in 15 hours. how long will it take to seal the parking lot if the two crews work ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.