If 7 men work on a piece of land in 5 days how long will it take 5 men to work on the same rate

+4
Answers (1)
  1. 13 June, 03:48
    0
    7 men will do the work in 5 days

    1 man will do 7*5=35

    so 5 men

    35/5 = 7 days

    have a nice day!
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If 7 men work on a piece of land in 5 days how long will it take 5 men to work on the same rate ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.