This? year, donnelly,? inc., will produce 60 comma 00060,000 hot water heaters at its plant in? delaware, in order to meet expected global demand. to accomplish? this, each laborer at the plant will work 200200 hours per month. if the labor productivity at the plant is 0.150.15 hot water heaters per labor? hour, how many laborers are employed at the? plant?

+4
Answers (1)
  1. 11 February, 04:49
    0
    Summary of problem.

    annual production = 60000 units

    work hours per worker = 200*12=2400 hours

    productivity = 0.15 unit / person-hour

    Need to calculate the number of workers/persons employed.

    Each unit requires 1 unit / 0.15 unit/person-hour

    = 1/0.15 person-hours / unit

    60000 unit requires 60000 units * 1/0.15 person-hours/unit

    = 400000 person-hours

    400000 person-hours requires 400000 person-hours / 2400 hours = 166.7 persons

    =>

    The plant has 167 labourers (assuming perfect attendance).
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “This? year, donnelly,? inc., will produce 60 comma 00060,000 hot water heaters at its plant in? delaware, in order to meet expected global ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.