It takes 15 electricians 24 days to wire a new housing subdivision. How many days would 18 electricians take to do the same job, assuming all electricians work at the same pace?

+5
Answers (1)
  1. 4 August, 12:51
    0
    So to set up this equation, you have to do

    Time1*Workers1=Time2*Workers2

    In this case, Time1=24 days, Workers1=15 electricians, and Workers2=18 electricians, and we have to solve for Time2

    Thus we get 15*24=18*Time2

    Time2=15*24/18=20 days
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “It takes 15 electricians 24 days to wire a new housing subdivision. How many days would 18 electricians take to do the same job, assuming ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.