If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish 4 houses?

+4
Answers (1)
  1. 4 May, 14:51
    0
    A = house

    3 days x 10 worker = a

    a = 30 work unit

    4a = 120 work unit

    120 work unit = 15 workers * y days

    y = 120/15 = 8 days

    i hope this isn't too confusing
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish 4 houses? ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.