Average maintenance costs are $1.50 per machine-hour at an activity level of 8,000 machine-hours and $1.20 per machine-hour at an activity level of 13,000 machine-hours. assuming that this activity is within the relevant range, total expected maintenance cost for a budgeted activity level of 10,000 machine-hours would be closest to:

+1
Answers (1)
  1. 20 March, 04:43
    0
    Assume that maintenance costs per machine may be modeled by the linear relation

    C = a + bx

    where

    x = machine hours

    a, b are constants.

    When x=8,000 hours, C=$1.50, therefore

    a + 8000b = 1.5 (1)

    When x=13,000 hours, C=$1.20, therefore

    a + 13000b = 1.2 (2)

    Subtract (2) from (1).

    a + 8000b - (a + 13000b) = 1.5 - 1.2

    -5000b = 0.3

    b = - 6 x 10⁻⁵

    From (1), obtain

    a = 1.5 - 8000 * (-6 x 10⁻⁵) = 1.98

    Therefore

    C = 1.98 - 6x10⁻⁵ x

    When machine hours is x=10,000, obtain

    C = 1.98 - 6x10⁻⁵ * 10000

    = 1.38

    Answer: $1.38
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Average maintenance costs are $1.50 per machine-hour at an activity level of 8,000 machine-hours and $1.20 per machine-hour at an activity ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.