Brett can plow out all the driveways on his street with his new four-wheel-drive truck in 6 hours. Using a snow blade on a lawn tractor, his neighbor can plow out the same number of driveways in 12 hours. How long would it take them to do the work together?

+3
Answers (1)
  1. 21 August, 10:37
    0
    4 hours

    Step-by-step explanation:

    The truck works twice as fast as a lawn tractor, so is equivalent to 2 of them. Together, they are equivalent to 3 lawn tractors, so can do the job in 1/3 the time of one of them: 4 hours.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Brett can plow out all the driveways on his street with his new four-wheel-drive truck in 6 hours. Using a snow blade on a lawn tractor, ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.