It takes 3600 person hours to complete a project. How many weeks will it take a team of 15 people to complete the job if each person works 8 hours, 5 days a week

+1
Answers (1)
  1. Today, 14:39
    0
    6 weeks

    Step-by-step explanation:

    x = # of weeks

    15 times 8 times 5 = 1 week,

    so 15 times 8 times 5 times x = 3600 is the equation

    Solve for x to get x = 6
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “It takes 3600 person hours to complete a project. How many weeks will it take a team of 15 people to complete the job if each person works ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.