To complete a task in 16 days a company needs

5 people each working in 6 hours per day

The company decides to have

8 people each working in 4 hours per day

Assuming that each person works at the same rate, how many days will the task take to complete

+4
Answers (1)
  1. 21 December, 08:42
    0
    15 days

    Step-by-step explanation:

    Total hours required =

    16*5*6 = 480

    Let n be the no. of days

    480 = n*8*4

    480 = 32n

    n = 480/32

    n = 15
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “To complete a task in 16 days a company needs 5 people each working in 6 hours per day The company decides to have 8 people each working in ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.