A plumber laying 500meters of drain pipe requires 20men working for 10days. What length in meters would be laid by 50men in 5days, if they all work at same rate?

+5
Answers (1)
  1. 27 December, 01:26
    0
    50men working in 5days will lay 100 meters

    Step-by-step explanation:

    If 20men working for 10days lays 500meters

    then, 1 man will lay 10,000 meters in 10 days

    also, 1 man will lay 1000 meters in 1 day

    If 1 man lays 1000 meters in 1 day,

    Then, 50 men will lay (1000 meters / 50); 20 meters in 1 day

    also, the same 50 men will lay (20 meters x 5days); 100 meters in 5 days.

    Therefore, 50men working in 5days will lay 100 meters
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A plumber laying 500meters of drain pipe requires 20men working for 10days. What length in meters would be laid by 50men in 5days, if they ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.