Ask Question
13 April, 12:13

A road crew must repave a road that is 3/4 miles long. They can repave 1/48 miles each hour. How long will it take the crew to repave the road?

+3
Answers (1)
  1. 13 April, 13:08
    0
    36 hours

    Step-by-step explanation:

    3/4 divided by 1/48

    KCF

    3/4*48/1 = 144/4 = 36
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A road crew must repave a road that is 3/4 miles long. They can repave 1/48 miles each hour. How long will it take the crew to repave the ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers